Developers canceled 1,996 U.S. power generation projects in 2025, removing roughly 266 GW of planned capacity from the future electric grid. That is close to one-quarter of today’s installed U.S. generation. More than 90% of the canceled projects were solar, wind, and battery storage.
These cancellations are happening while electricity demand is rising across nearly every region. Data centers, AI workloads, electrification of buildings and vehicles, and industrial reshoring are driving sustained load growth across the electric grid. Demand is real and accelerating. Supply is being reduced before it ever reaches the grid.
The reasons are structural. Interconnection queues stretch for years, with network upgrade costs disclosed late and often large enough to break project economics. Permitting timelines are slow and fragmented. Transmission expansion on the electric grid lags demand growth.
Policy uncertainty and trade exposure increase capital costs, and long delays erode returns, particularly for storage and renewable projects that depend on speed to market.
Higher Electricity Costs Come First
When future supply is removed, markets tighten. Utilities lean harder on existing generation, much of it older and more expensive to operate on the electric grid.
Capacity scarcity raises wholesale prices, which flow directly into retail rates. Customers pay more even though the canceled projects were never built.
Reliability Risk Follows on the Electric Grid
Reserve margins shrink when planned capacity disappears. The electric grid becomes more sensitive to heat waves, cold snaps, and equipment failures. Emergency measures move from rare events to planning assumptions.
Capital Also Becomes More Expensive
When projects face multi-year interconnection and permitting delays, timeline risk increases. Capital sits idle longer. Lenders price that delay with higher interest rates. Cancellation risk gets priced into the entire sector. Even strong projects inherit a higher perceived failure rate.
As capital providers retreat, competition for financing shrinks, leading to higher spreads, stricter covenants, and more equity required upfront. Those higher financing costs show up in power purchase agreements, utility rate cases, and infrastructure spending. They ultimately land on customer bills.
The core point is simple.
The technology did not fail.
Demand did not fail.
The system failed to deliver projects to the grid.
Canceling 1,996 power projects does not reduce demand. It shifts cost and risk downstream. The impact will appear steadily through higher electricity prices, tighter reserve margins, and reduced tolerance for grid stress.
When supply is removed and demand keeps growing, the ending is predictable.
We pay for it.